Accuracy in order fulfillment time of the
company's promise and product quality are in line with
expectations, as well as the fees charged are considered
reasonable is unsur-satisfaction elements that must be
met by the company to the consumer. PT. XXX is a
manufacturing company engaged in the manufacture of
products such as car parts car roof, hood and fenders.
Based on data from the company, according to the
company in 2018 many mismatches or delayed against
the schedule or machines that have been made. The
purpose of this study to determine the time of receipt to
the method Expenses Oriented Manufacturing Control
(LOMC) in which the time of receipt of the order is
based on a calculation that takes into account the lead
time delivery time manufacturing orders for customers,
available capacity at each work station, the processing
time at the work station and the flow of production on
the production floor and also determine the critical path
on the activities to be undertaken by the NCB 8 engine.
By using the Load method Oriented Manufacturing
Control by observing the available capacity, delivery
times and priority sequence obtained in the acceptance
of the project and also made a critical path analysis of
the project to be undertaken by the NCB 8 engines like
PL, BJN, BJ, BN, bY. and K2. This shows that the
calculation time of order entry order using expense
method Oriented Manufacturing Control (LOMC) is
more accurate than the actual method. delivery times
and priority sequence obtained in the acceptance of the
project and also made a critical path analysis of the
project to be undertaken by the NCB 8 engines like PL,
BJN, BJ, BN, BY. and K2. This shows that the
calculation time of order entry order using expense
method Oriented Manufacturing Control (LOMC) is
more accurate than the actual method. delivery times
and priority sequence obtained in the acceptance of the
project and also made a critical path analysis of the
project to be undertaken by the NCB 8 engines like PL,
BJN, BJ, BN, BY. and K2. This shows that the
calculation time of order entry order using expense
method Oriented Manufacturing Control (LOMC) is
more accurate than the actual method.
Keywords : Critical Path, Project, Date Reachive.