Construction projects comes across various
milestones, resulting into delay in execution of project,
hence there is need to improve techniques in planning so
that project is carried out within stipulated time. The
LOBST (Line Of Balance Scheduling Technique) is a
scheduling method which makes the operations to be
carried out effectively and allows activity can be
performed continuously and efficiently in each
consecutive unit. Line Of Balance Scheduling Technique
is a significant technique that plays important role in
repetitive construction project. Lack of awareness of
proper method and techniques increases cost and project
completion time. It becomes very important to adopt
proper methodology while doing the housing project for
low income group. This paper aims to evaluate the real
application of line of balance in low income housing
scheme. Case study of low-income housing project by
MHADA at Talegaon-Dabhade,Pune. Also supports the
method developed in the paper. The findings point out
significant controlling benefits of LOB is comparing with
GANNT CHART Method in the project and addresses
limitations showing the efficient use of LOB. VICO
CONTROL software is used to schedule the project by
line of balance technique. It is observed that this method
increases line efficiency and minimizes smoothness index.
Keywords : Repetitive Scheduling Method (RSM), Line Of Balance (LOB),Cycle Time(CT),Line Efficiency(LE),Work Station(WS).